发表于 1-3-2017 04:01 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
31 Dec 2016 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 31 Dec 2016 | 31 Dec 2015 | 31 Dec 2016 | 31 Dec 2015 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 5,772 | 3,104 | 15,940 | 11,552 | 2 | Profit/(loss) before tax | 434 | -1,293 | 611 | -2,633 | 3 | Profit/(loss) for the period | 434 | -1,292 | 611 | -2,632 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | 434 | -1,292 | 611 | -2,632 | 5 | Basic earnings/(loss) per share (Subunit) | 0.19 | -1.03 | 0.33 | -2.13 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2100 | 0.2100
|
|
|
|
|
|
|
|
|
发表于 19-4-2017 05:19 AM
|
显示全部楼层
本帖最后由 icy97 于 22-4-2017 04:06 AM 编辑
BTM资源拟与外企联手打造4.35亿废物转至能源发电厂
Adela Megan Willy/theedgemarkets.com
April 17, 2017 20:45 pm MYT
(吉隆坡17日讯)BTM资源(BTM Resources Bhd)计划与两家中国公司--华西能源国际股份有限公司(China Western Power International)和四川电力建设2公司(Sichuan No 2 Electric Power Construction Company)合作,在马六甲打造一座价值4亿3500万令吉的市政废物转至能源(WTE)发电厂。
BTM资源今日透过大马交易所发文告报备,该集团已和华西能源及四川电力于上周五(4月14日)签订一项谅解备忘录(MoU),其中清楚阐明涉及此项目的各方意图。
根据文告,这座WTE发电厂每日的产能不低于1000吨。
华西能源涉及投资、工程、商业和管理服务业务,而四川电力在再生能源项目的发展、投资、建设和营运有着极丰富的经验。
在这项MoU下,所有三方将通过一家特殊用途公司(SPV),联手投资以标得发电项目。
这个项目的投资总额估计为4亿3500万令吉。
BTM资源表示,西华能源和四川电力将负责这个项目的工程、采购、建设和调试(EPCC)的所有融资成本,并全额资助与此相关的技术开发成本。
“本集团将透过MoU与此次合作的平台,借助四川电力在发电项目的声誉、经验与地位。这将多元化收入来源,以及未来为集团贡献盈利。”
(编译:倪嫣鴽)
Type | Announcement | Subject | MEMORANDUM OF UNDERSTANDING | Description | MEMORANDUM OF UNDERSTANDING BETWEEN BTM RESOURCES BERHAD,("THE COMPANY") CHINA WESTERN POWER INTERNATIONAL PTE LTD AND SICHUAN NO.2 ELECTRIC POWER CONSTRUCTION COMPANY (COLLECTIVELY KNOWN AS "THE PARTIES") FOR THE ESTABLISHMENT OF A RM435.0 MILLION MUNICIPAL SOLAD WASTE TO ENERGY GENERATION PLANT IN THE STATE OF MELAKA | |
|
|
|
|
|
|
|
|
发表于 13-6-2017 07:39 PM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
31 Mar 2017 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 31 Mar 2017 | 31 Mar 2016 | 31 Mar 2017 | 31 Mar 2016 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,126 | 2,935 | 3,126 | 2,935 | 2 | Profit/(loss) before tax | 102 | -43 | 102 | -43 | 3 | Profit/(loss) for the period | 102 | -43 | 102 | -43 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | 102 | -43 | 102 | -43 | 5 | Basic earnings/(loss) per share (Subunit) | 0.08 | -0.03 | 0.08 | -0.03 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2100 | 0.2100
|
|
|
|
|
|
|
|
|
发表于 30-8-2017 04:40 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
30 Jun 2017 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 30 Jun 2017 | 30 Jun 2016 | 30 Jun 2017 | 30 Jun 2016 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,295 | 3,233 | 6,421 | 6,166 | 2 | Profit/(loss) before tax | 148 | 38 | 250 | -5 | 3 | Profit/(loss) for the period | 148 | 38 | 250 | -5 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | 148 | 38 | 250 | -5 | 5 | Basic earnings/(loss) per share (Subunit) | 0.12 | 0.03 | 0.20 | 0.00 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2100 | 0.2100
|
|
|
|
|
|
|
|
|
发表于 22-10-2017 07:20 AM
|
显示全部楼层
BTM资源新大股东.近期料浮现
(吉隆坡21日讯)消息人士指出,小资本木材公司BTM资源(BTM,7188,主板工业产品组)料在未来一至二周内,迎来新大股东──来自香港的私募基金(PE)公司。
消息人士向《The Edge》表示,该香港投资公司已握有BTM资源3.1%股权,并将透过包括私下配售和转换凭单的方式,增持股权。
《彭博社》数据显示,BTM资源在本月10日,进行3项共400万股或3.1%的股权交易,每股售价为10仙。
“这批(400万股)是在场外进行,而目前(香港投资公司)在BTM资源的持股将增至约2500万股。”
据探悉,BTM资源建议进行私下配售,发售最多1280万股新股,相等于缴足资本的10%。
消息人士指出,无论该公司是否进行私下配售,香港私募基金公司也将崛起成为大股东,主要是因为后者目前在不断吸纳已发行的凭单。
文章来源:
星洲日报/财经‧2017.10.21 |
|
|
|
|
|
|
|
发表于 24-10-2017 03:10 AM
|
显示全部楼层
Type | Announcement | Subject | OTHERS | Description | BTM RESOURCES BERHAD ("BTM" OR " THE COMPANY") | We refer to the article in page 14 of The Edge dated 23 October 2017, with the headline "HK PE firm to emerge as BTM Resources' substantial shareholders ?".
In relation thereto,the Board of Directors of BTM wish to clarify that the Company is in the midst of deliberating to undertake a fund raising exercise which the Company will make the necessary announcements once it has been finalised.
This announcement is dated 23 October 2017. |
|
|
|
|
|
|
|
|
发表于 26-11-2017 06:21 AM
|
显示全部楼层
本帖最后由 icy97 于 28-11-2017 02:39 AM 编辑
Type | Announcement | Subject | OTHERS | Description | BTM RESOURCES BERHAD'S ("BTM" OR "THE COMPANY") ACQUISITION OF A SUBSIDIARY | With reference to the announcement made on 17 April 2017,where a Memorandum of Understanding between BTM Resources Berhad ("the Company"),China Western Power International Private Limited and Sichuan No.2 Electric Power Construction Company (collectively known as "The Parties") for the establihment of a RM 435.0 million Municipal Solid Waste to Energy Generation Plant in the State of Melaka.
The Board of Directors of BTM Resources Berhad wishes to announce that the Company has on 22 November 2017 acquired 51.00% of share capital of BTM Western Power Green Energy Sdn Bhd (Company no.1228087-M) for a consideration of Ringgit Malaysia Five Hundred and Ten only (RM 510.00) representing 510 shares of RM 1.00 each.
BTM Western Power Green Energy Sdn Bhd is a company incorporated under The Companies Act 2016 on 20 April 2017 and having its Registered Office at 26-2,Lorong 6E/91,Taman Shamelin Perkasa,56100 Kuala Lumpur.
BTM Western Power Green Energy Sdn Bhd will be a Joint Venture Company between BTM Resources Berhad and China Western Power International Private Limited and the shareholding structure is to be as follows: BTM Resources Berhad :51.00% China Western Power International Private Limited :49.00%
The Pricipal activities of this Joint Venture Company is to act as a project developer to develop a set up of a Municipal Waste to Energy Generation Plant ("WtE Plant") with a capacity of not less than 1,000 tons/day in the State of Melaka,Malaysia,subject to the approval of the relevant authorites.
None of the Directors,major shareholders and persons connected with the Directors/or major shareholdres of BTM Resources Berhad,have any interest,direct or indirect, in this acquisition.
This acqusition does not required the approval of the shareholders of BTM Resources Berhad.
This announcement is dated 22 November 2017. |
|
|
|
|
|
|
|
|
发表于 2-12-2017 02:54 AM
|
显示全部楼层
本帖最后由 icy97 于 10-12-2017 05:08 AM 编辑
BTM资源甲州建垃圾焚烧发电厂
2017年11月28日
(吉隆坡27日讯)BTM资源(BTM,7188,主板工业产品股)子公司BTM Western Power Green Energy私人有限公司(简称BTMWP),获颁工程、采购、施工、调试和金融(简称EPCC + F)合约。
BTM资源向交易所报备,为了执行该项目,BTMWP今天与SEPCO电力建设公司(简称SEPCO)签署暂定协议。
根据协议,BTMWP将发展马六甲的垃圾焚烧发电厂项目,每日处理量不少于1000吨。
BTMWP正在申请EPCC+F的承包商资格;而SEPCO具备这方面的资格。
SEPCO将与BTMWP一起进行必要的前期工作、一般项目的工程、采购、建设和调试,以及安排和测试项目的全面金融。
拍伙四川电力
BTM资源称,这项协议为公司提供进军SEPCO熟悉的电力项目,且多元化公司的收入来源,贡献未来盈利。
回顾4月,BTM资源与中国西部电力国际私人有限公司、四川电力和中华民国签署了解备忘录,在马六甲建设处理城市生活垃圾的能源发电厂,总值4亿3500万令吉。SEPCO是四川电力的控股公司。【e南洋】
Type | Announcement | Subject | OTHERS | Description | HEADS OF AGREEMENT BETWEEN BTM WESTERN POWER GREEN ENERGY SDN BHD AND SEPCO ELECTRIC POWER CONSTRUCTION CORPORATION FOR THE AWARD OF A EPC+F CONTRACT FOR A MUNICIPAL SOLID WASTE TO ENERGY GENERATION PLANT IN THE STATE OF MELAKA | For the details of announcement please refer to the attachment file. | http://www.bursamalaysia.com/market/listed-companies/company-announcements/5616533
|
|
|
|
|
|
|
|
发表于 5-12-2017 03:39 AM
|
显示全部楼层
Type | Announcement | Subject | NEW ISSUE OF SECURITIES (CHAPTER 6 OF LISTING REQUIREMENTS)
FUND RAISING | Description | BTM RESOURCES BERHAD ("BTM" OR THE "COMPANY")PROPOSED PRIVATE PLACEMENT OF UP TO 10% OF THE ISSUED SHARES IN BTM | On behalf of the Board of Directors of BTM, M&A Securities Sdn Bhd wishes to announce that the Company proposes to undertake a proposed private placement of up to 10% of the issued shares of BTM (“Proposed Private Placement”).
Kindly refer to the attached announcement for further details of the Proposed Private Placement.
This announcement is dated 28 November 2017. | http://www.bursamalaysia.com/market/listed-companies/company-announcements/5619789
|
|
|
|
|
|
|
|
发表于 6-12-2017 02:15 AM
|
显示全部楼层
Type | Announcement | Subject | OTHERS | Description | HEADS OF AGREEMENT BETWEEN BTM WESTERN POWER GREEN ENERGY SDN BHD AND SEPCO ELECTRIC POWER CONTRUCTION CORPORATION FOR THE AWARD OF A EPC+F CONTRACT FOR A MUNICIPAL SOLID WASTE TO ENERGY GENERATION PLANT IN THE STATE OF MELAKA | With reference to the announcement made on 17 April 2017 and 27 November 2017,the Board of Directors of BTM Resources Berhad ("BTM") is please to further announce the following:-
1.BTM Western Power Green Energy Sdn Bhd ("BTMWP") has submitted its application and proposal to develop a Waste Incineration Power Plant Project located in the State of Melaka with capacity of not less than 1,000 tons ("the Project") to the relevant authority of the State Government of Melaka and is now pending approval.
2. BTMWP will develop,build,own and operate the Project and BTMWP has not set any time frame for this Project.
3. This Heads of Agreement will remain effective until a formal Engineering,Procurement,Construction and Commissioning with Finance ("EPC+F") Contract containing the detailed terms and conditions including inter-alia duration,cost of the Project is entered into between the Parties, at a date to be determined later upon receiving the necessary approvals from the relevant authorities for the Project.
This announcement is dated 29 November 2017 |
|
|
|
|
|
|
|
|
发表于 9-12-2017 06:12 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
30 Sep 2017 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 30 Sep 2017 | 30 Sep 2016 | 30 Sep 2017 | 30 Sep 2016 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,163 | 4,000 | 9,584 | 10,168 | 2 | Profit/(loss) before tax | 204 | 182 | 454 | 177 | 3 | Profit/(loss) for the period | 202 | 182 | 452 | 177 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | 202 | 182 | 452 | 177 | 5 | Basic earnings/(loss) per share (Subunit) | 0.16 | 0.15 | 0.36 | 0.14 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2200 | 0.2100
|
|
|
|
|
|
|
|
|
发表于 15-2-2018 04:09 AM
|
显示全部楼层
1. Details of Corporate Proposal | Involve issuance of new type/class of securities ? | No | Types of corporate proposal | Private Placement | Details of corporate proposal | ADDITIONAL LISTING APPLICATION FOR THE LISTING OF AND QUOTATION FOR UP TO 15,478,900 NEW ORDINARY SHARES IN BTM RESOURCES BERHAD ON THE MAIN MARKET OF BURSA MALAYSIA SECURITIES BERHAD TO BE ISSUED PURSUANT TO A PROPOSED PRIVATE PLACEMENT EXERCISE | No. of shares issued under this corporate proposal | 7,849,400 | Issue price per share ($$) | Malaysian Ringgit (MYR) 0.2200 | Par Value($$) (if applicable) | Malaysian Ringgit (MYR) 0.000 | Latest issued share capital after the above corporate proposal in the following | Units | 136,344,188 | Issued Share Capital ($$) | Malaysian Ringgit (MYR) 28,287,857.000 | Listing Date | 15 Feb 2018 |
|
|
|
|
|
|
|
|
发表于 7-3-2018 01:47 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
31 Dec 2017 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 31 Dec 2017 | 31 Dec 2016 | 31 Dec 2017 | 31 Dec 2016 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,188 | 5,771 | 12,772 | 15,939 | 2 | Profit/(loss) before tax | -1,229 | 228 | -775 | 405 | 3 | Profit/(loss) for the period | -1,229 | 228 | -777 | 405 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | -1,225 | 229 | -773 | 406 | 5 | Basic earnings/(loss) per share (Subunit) | -0.96 | 0.18 | -0.61 | 0.32 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2300 | 0.2100
|
|
|
|
|
|
|
|
|
发表于 14-4-2018 04:46 AM
|
显示全部楼层
1. Details of Corporate Proposal | Involve issuance of new type/class of securities ? | No | Types of corporate proposal | Private Placement | Details of corporate proposal | PRIVATE PLACEMENT OF UP TO 10% OF THE ISSUED SHARES IN BTM RESOURCES BERHAD | No. of shares issued under this corporate proposal | 5,000,000 | Issue price per share ($$) | Malaysian Ringgit (MYR) 0.1500 | Par Value($$) (if applicable) | Malaysian Ringgit (MYR) 0.000 | Latest issued share capital after the above corporate proposal in the following | Units | 141,344,188 | Issued Share Capital ($$) | Malaysian Ringgit (MYR) 29,037,857.000 | Listing Date | 16 Apr 2018 |
|
|
|
|
|
|
|
|
发表于 19-4-2018 04:49 AM
|
显示全部楼层
本帖最后由 icy97 于 22-4-2018 03:01 AM 编辑
Type | Announcement | Subject | OTHERS | Description | PROPOSED ACQUISITION OF 60% EQUITY INTEREST IN ZULIKHA MURNI SDN BHD ("ZWSB") | With reference to the Company's announcements dated 22 April 2016, 26 April 2016 and 27 April 2016, the Board of Directors of BTM Resources Berhad wishes to announce that the Company 's subsidiary BTM Marketing & Trading Sdn Bhd sent a Notice of Termination dated 16 April 2018 to the Vendor of Shares of Zulikha Murni Sdn Bhd ("ZMSB") to terminate the Shares Sale Agreement dated 22 April 2016.
The Notice of Termination was sent to Vendor of Shares due to the non-receipt by the Company of the original Temporary Occupancy Licence ("TOL") for the first 100 plots of TOL Land duly issued by the Selangor State Authoruty in the Name of ZMSB.
This announcement is dated 17 April 2018. |
|
|
|
|
|
|
|
|
发表于 27-5-2018 02:45 AM
|
显示全部楼层
本帖最后由 icy97 于 2-6-2018 07:45 AM 编辑
Type | Announcement | Subject | OTHERS | Description | BTM WESTERN POWER GREEN ENERGY SDN. BHD. AND SEPCO ELECTRIC POWER CONSTRUCTION CORPORATION FOR A PROPOSED MUNICIPAL SOLID WASTE TO ENERGY GENERATION PLANT IN THE STATE OF MELAKA | With reference to the Company's announcements made on 29 November 2017 and 2 January 2018, the Board of Directors of BTM Resources Berhad wishes to announce that on 23 May 2018, BTM Western Power Green Energy Sdn Bhd has received a letter dated 3 May 2018 from Jabatan Pengurusan Sisa Pepejal Negara ( Department of National Solid Waste Management) informing that the Department is not abled to consider the application of setting- up a Municipal Solid Waste To Energy Generation Plant in the State of Melaka.
This announcement is dated 23 May 2018. |
|
|
|
|
|
|
|
|
发表于 11-6-2018 01:53 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
31 Mar 2018 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 31 Mar 2018 | 31 Mar 2017 | 31 Mar 2018 | 31 Mar 2017 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,617 | 3,126 | 3,617 | 3,126 | 2 | Profit/(loss) before tax | -426 | 102 | -426 | 102 | 3 | Profit/(loss) for the period | -426 | 102 | -426 | 102 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | -426 | 102 | -426 | 102 | 5 | Basic earnings/(loss) per share (Subunit) | -0.32 | 0.08 | -0.32 | 0.08 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2200 | 0.2200
|
|
|
|
|
|
|
|
|
发表于 1-9-2018 05:19 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
30 Jun 2018 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 30 Jun 2018 | 30 Jun 2017 | 30 Jun 2018 | 30 Jun 2017 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,650 | 3,295 | 7,267 | 6,421 | 2 | Profit/(loss) before tax | -665 | 148 | -1,091 | 250 | 3 | Profit/(loss) for the period | -665 | 148 | -1,091 | 250 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | -662 | 148 | -1,088 | 250 | 5 | Basic earnings/(loss) per share (Subunit) | -0.47 | 0.12 | -0.80 | 0.20 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2100 | 0.2200
|
|
|
|
|
|
|
|
|
发表于 27-12-2018 05:45 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
30 Sep 2018 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 30 Sep 2018 | 30 Sep 2017 | 30 Sep 2018 | 30 Sep 2017 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 4,663 | 3,163 | 11,930 | 9,584 | 2 | Profit/(loss) before tax | 127 | 204 | -964 | 454 | 3 | Profit/(loss) for the period | 127 | 202 | -964 | 452 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | 127 | 202 | -961 | 452 | 5 | Basic earnings/(loss) per share (Subunit) | 0.09 | 0.16 | -0.70 | 0.36 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2100 | 0.2200
|
|
|
|
|
|
|
|
|
发表于 9-3-2019 06:55 AM
|
显示全部楼层
SUMMARY OF KEY FINANCIAL INFORMATION
31 Dec 2018 |
| INDIVIDUAL PERIOD | CUMULATIVE PERIOD | CURRENT YEAR QUARTER | PRECEDING YEAR
CORRESPONDING
QUARTER | CURRENT YEAR TO DATE | PRECEDING YEAR
CORRESPONDING
PERIOD | 31 Dec 2018 | 31 Dec 2017 | 31 Dec 2018 | 31 Dec 2017 | $$'000 | $$'000 | $$'000 | $$'000 |
1 | Revenue | 3,685 | 3,179 | 15,615 | 12,763 | 2 | Profit/(loss) before tax | -1,440 | -1,951 | -2,404 | -1,497 | 3 | Profit/(loss) for the period | -1,440 | -1,279 | -2,404 | -827 | 4 | Profit/(loss) attributable to ordinary equity holders of the parent | -1,438 | -1,273 | -2,399 | -821 | 5 | Basic earnings/(loss) per share (Subunit) | -1.02 | -0.99 | -1.73 | -0.65 | 6 | Proposed/Declared dividend per share (Subunit) | 0.00 | 0.00 | 0.00 | 0.00 |
|
| AS AT END OF CURRENT QUARTER | AS AT PRECEDING FINANCIAL YEAR END | 7
| Net assets per share attributable to ordinary equity holders of the parent ($$) | 0.2000 | 0.2200
|
|
|
|
|
|
|
|
| |
本周最热论坛帖子
|